Why keep a site diary?
The site diary is the memory of the site. Months later, it shows who was there on which day, what was done, what the weather was like and what got in the way. In disputes about delays, additional work or defects, it is often the most important evidence.
What goes in it
- date, weather and temperature,
- staff present, your own people and other contractors,
- work carried out,
- deliveries and machines used,
- obstructions and interruptions, for example due to weather or missing preparatory work,
- instructions from site management, visits, acceptances,
- special incidents, accidents, defects — ideally with a photo.
Five tips
- Write it every day, not on Friday for the whole week.
- Be specific: «Electrician absent, cables on upper floor not pulled» instead of «delay».
- Dated photos say more than any description.
- Record instructions, including verbal ones, with name and time.
- Have it countersigned regularly if the contract provides for it.
To print: our site diary template as PDF and Excel.
Reports as a basis
If you keep your reports digitally, you already have much of what the site diary needs: in Baurapport.ch, the hours, the work carried out, the materials and the photos are stored per site and day, along with the chat and what was agreed in it. The app does not replace a proper site diary, but it supplies the facts for it.
Frequently asked questions
Who keeps the site diary?
Usually site management; many contractors also keep their own to record their side. What applies is set out in the contract.
How long should it be kept?
At least as long as claims under the contract for work can be made — certainly until the warranty has expired.
Is a collection of photos enough?
Photos help a lot, but they do not replace the entries on staff, work and obstructions.